Title: CSCI321 Project Group Meeting 20
Time: Friday, 27 September, 2013 14:00
Location: Building 3, UOW
Attendees: Hong Wi Yew, Guanqiao Huang, Xing Pan, Qing Ren
Recorder: Guanqiao Huang
Objective:
Complete UML diagram
Continued design the User interface
Complete some diagram
We continued fix some problem in UML diagram, such as use case diagram, sequence diagram and activity diagram.
In use case part, except use case diagram, we also need to write the scenario of each use case.
These include use case name, primary actor, supporting actors, summary, pre-conditions, normal flow of events, extensions,post-conditions.
To be specific,
Use case name: the same name as each use case in use case diagram.
Actor: we separate two kind of actor, which are student and developer.
Summary: Specific description of use case
Conditions: Pre conditions of each use case
Flow of Events: In this part we need according to the user inter face, so we need to draw a basic interface. And then each steps following the user interface.
And so on
Continued design the User interface
We continued discuses user interface, each one got their own idea about user interface, we draw several style about Hash Kit on the paper, it is difficult to summarize those user interface.
Some user interface very good but we might difficult to code it, some interface is very basic we might easy to code. Actually on the draft user interface, we need to focus on the basic function.