Objectives:
Meeting with supervisor
Discussion about presentation and requirement
Meeting with supervisor
We meeting with supervisor on Friday each week. In this week, we ask our supervisor something about our presentation in week 6. Because we are not sure our PPT meet the requirement.
There is some note for improve our presentation
1. Add a Introduction about Hash function
2. Add some business purpose about Hash
3. On deployment environment part, we need to give some evidence or reason, explain why.
4. On development environment part, why .Net? why use C++?
5. Project purpose, remove GUI, make sure the platform, researcher->Linux, Educational->Windows
6. Explain why spiral model
Discussion about presentation and requirement
We decide Hong Wi as our presenter, and we edit the ppt for presentation in week 6. We use brain storm to thinking the requirement specification. However, the efficiency is not high, so we are going to spend two days (weekend) to thinking about the specification, and we will summarize a draft requirement specification next week.